The year is 2012, and the cost of microturbines has finally come down to make them a viable option for on-site power generation. In addition, there's been a tremendous proliferation of wireless technology to enable conveniences such as viewing medical records and x-rays on a projection screen right at the patient's bed.
But before a healthcare facility can start bringing in such new technology, cost and feasibility must be evaluated. A large part of this analysis is determining if the facility's infrastructure is robust and flexible enough to support such M/E advances. That question all goes back to how much foresight was built into the planning and design of the hospital's infrastructure.
For instance, a general rule of thumb applied by Heery International's Director of Engineering Richard Snyder when specifying an electrical system is to build in 30% additional capacity—simple, as opposed to going back to the main hub to upgrade electrical capacity for new equipment, which can be a very big expense.
Snyder's Heery colleague, Joe Gottardy, PE, mechanical department manager, Atlanta, adds, “When sizing ducts and piping, we try to add 20% additional capacity at the end of the run in order to easily accommodate new systems in the future.” Gottardy also recommends oversizing air filtration systems to accommodate increased air-flow rates since code requirements are always changing.
Engineer Clark Brenner, PE, director of healthcare, Arnold & O'Sheridan, Southfield, Michigan, advises, “Air-handling systems need to accommodate additional filtration technologies and infection control technologies, such as ultraviolet radiation, heat-recovery options, and germicidal, high-performance, low-pressure air purification systems.”
Another way Brenner's firm takes future needs into account is by anticipating that a hospital's requirement for controlling heat load generated by medical equipment and building systems will grow considerably over the years. Says Brenner, when designing the HVAC system: “We provide a central process water cooling loop that may be extended on each floor or tapped into to provide easy installation of process cooling equipment. This has proven to be very beneficial in many areas where additional cooling may be needed to offset the heat loads from new electronic equipment that was not planned for.”
Similarly, for the placement of mechanical and electrical equipment, Kirk Pesta, PE, associate mechanical engineer, Harley Ellis Devereaux, Detroit, recommends grated floors, as opposed to concrete, for mechanical rooms. “We want to always have a vertical element available to the hospitals, and grated floors make it easy to go in and add systems,” he explains. However, keeping in mind that the hospital may want to build on additional floors in the future, Pesta tries to avoid placing mechanical equipment on the roof.
On the electrical side, Pesta's colleague, Stephen Milz, PE, an associate electrical engineer with the firm, emphasizes the importance of working with programmers and space planners up-front to negotiate adequate closet space per floor for current and future low-voltage cabling, as well as ceiling space for running horizontal cable trays. He adds that, for the ceiling, the space must not only be sufficient for the cabling itself, but proper clearances are required by technicians for easy access to the trays.
One electrical strategy that Steve Yanke, PE, director of engineering, OWP/P, Phoenix, employs is putting switchgear on drawer slides, as opposed to bolting it onto the busway. This way, when circuit breakers need to be changed out, it's a simple procedure.
When all is said and done, though, when planning for the future, spacious design isn't simple—every square foot of real estate comes with a big price tag, notes Lou Irvine, PE, project electrical engineer, Bala Consulting Engineers, King of Prussia, Pennsylvania. James Moler, PE, manager of engineering systems for Turner Healthcare, Brentwood, Tennessee, concurs: “Facilities and budgets can't really withstand too many what-ifs. Things which are being done are very programmatic and for the short-term. In general, hospitals don't have the budget to support long-range futuristic designs. Planning has to be based on things that are pretty well known and already in the pipeline.” Joey Caldwell, PE, senior plumbing engineer, HSMM, Roanoke, Virginia, agrees: “It's impossible to program additional space not really knowing what technology will be coming into the hospital in the future.”
Even so, it behooves planners and designers to pay attention to certain trends, such as a fairly recent surge of interest in back-up power. “In the past, a little bit of downtime was acceptable, but there's been a total shift to zero tolerance for downtime, so that's how systems have to be designed,” explains Steve Yanke. Joe Gottardy points out that the codes don't require putting chillers on the emergency back-up system, and yet this is something most clients are now asking for, although in many cases, the original system wasn't designed with the capacity to take on a chiller or other non-essential systems.
In the experience of the Orlando-based firm TLC Engineering for Architecture, “We've actually had requests to back up the entire facility,” says Vincent Rea, PE, LEED AP, a senior electrical engineer. “So we need to provide for a future allocation of generation up front in the design.”
Back-up power aside, designers must also consider the sheer rate at which electrical apparatuses are increasing in hospitals. “In 2004, there were typically 50 to 52 electrical systems in a hospital and, in 2007, there a more than 100. That's a significant increase,” points out Vlad Torskiy, AIA, vice-president of HOK's healthcare business unit, Chicago.
As far as what to expect in the realm of trendy new technology, wireless tops the list. Even though a number of issues still need to be sorted out, such as security and formatting, the adoption of wireless is impending throughout healthcare, say the experts. Consequently, hospitals must brace themselves for supporting larger bandwidths and multiple frequencies to empower increasing numbers of mobile devices and robotics.
“As time goes on we will have more ‘smart’ devices in the field,” predicts Clark Brenner. “For example, microprocessors will be installed in anything from door hardware to bathroom sinks. Having the communications backbone that can absorb these additional devices will be important.”
Also, in the wake of the back-up power trend, more and more hospitals are expressing interest in getting off the grid. As a result, consulting engineers are being asked to look at things like fuel cells, photovoltaics, and microturbines. “While the cost of such technologies is still high, they should be coming down,” anticipates TLC's Rea.
This being the case, it's important to introduce such possibilities now because PV arrays or a microturbine farm require a decent amount of space, and that is something that must of course be planned for.
Regarding other technological advances, water re-use and energy-recovery systems that utilize waste heat will most likely be a trend, particularly since hospitals are some of the largest energy and water users in a city.
“Hospitals are huge energy hogs that exhaust a lot of air,” says Pesta. Brenner adds, “Many processes in healthcare, such as water conditioning systems, often dispose of thousands of gallons of usable water that could alternatively be used for nonpotable water applications. Plumbing systems should be designed to allow for the recovery of this water and engineers should plan on space to allow for gray water and storm water recovery systems.”
One piece of advice from TLC's Mark A. Gelfo, PE, LEED AP, principal and division director, Jacksonville: “One of the specific things we do to help prepare our hospitals to accept new technologies is to specify control systems with open communications protocols. This allows almost any new system or old system with a new intelligent controller to be tied to the building management system.”
The future is now
At the end of the day, Gelfo sums it up well: “The needs, trends and technologies we're seeing in hospitals are always changing and it's harder and harder to plan the infrastructure for the future. But, in general, providing as much flexibility as possible for the hospital's infrastructure is the key.” Whether it's planning for on-site power generation or beefing up a hospital's M/E infrastructure to support new technology, making such important planning decisions with a little foresight today can save tens of thousands of dollars tomorrow. TCV