Anticipating the Big One

September 1, 2008
| Share | Print

Southern California is expected to be hit by a massive earthquake (6.7) in the next three decades, according to a statewide study. While seismologists and citizens await the possible big one, the building industry is using new and unique methods to make structures safer in the event of a major jolt. The industry has been diligently working to make sure we don't have the collapse of buildings and structures, much like what happened when the 6.7-magnitude earthquake rocked Northridge, California, in 1994.

A little further south in San Diego County, the granite bedrock, found in some parts of the region, provides more resistance to damage from tremors, while other buildings are built on top of terrace deposit, which includes ocean sediments and red, silty sands that are softer and therefore amplify the rocking motion of an earthquake. However, government officials and industry leaders contend that even large structures in San Diego could weather a large temblor if built and secured properly.

For example, in an effort to seismically secure the new $260 million Rady Children's Hospital Acute Care Pavilion in San Diego (figure 1), McCarthy Building Companies, Inc., chose a Micro-Pile application of a Dywidag tie-down anchor rod system. Considered a novel approach in the healthcare design world, a tie-down prevents the building's foundations from being uplifted during an earthquake. The Uniform Building Code requires that the foundation of structures be designed to resist the upward force of a seismic event. The designers of the Rady project came up with the Micro-Pile technology because it required the least amount of redesign and would allow a relatively short resubmission time back to the Office of the Statewide Health Planning and Development for its final approval.

Construction site for new $260 million Rady Children's Hospital Acute Care Pavillion, being built by McCarthy Building Companies



It is not unusual for structural foundations to be supplemented with caissons or driven piles, should the soil conditions dictate the need to literally float the building with the assistance of these foundation elements and secure the foundation to the bedrock layer below. This insures the solid embedment of the foundation supports and makes sure that any building settling will be minimal and uniform.

At Rady, the problem was not how to float the building foundation, but how to hold it down in case of a seismic event. To complicate the problem, the need to add tie-down anchors was determined late in the preconstruction process, requiring the structural engineer to either redesign the entire foundation or come up with an acceptable hold-down alternative.

To keep the project on schedule, the project architect Anshen+Allen and the structural engineer KPFF, analyzed the problem and selected the tie-down technology—which is not commonly used in healthcare projects in California—as the most effective solution and means to keep the project on schedule. Steve Van Dyke, McCarthy Building Companies' senior project manager of the project, was very familiar with the Dywidag systems used on wall tie-backs, but had not encountered the Micro-Pile system on previous hospital construction. If the seismic safety requirement had been identified during the programming stage of the project, the structural engineer may have chosen a different method, such as beefing up the foundation members or using caissons to add additional anchorage to the building foundation.

Page
of 2Next

Comments

Post new comment

CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.
Image CAPTCHA
Enter the characters shown in the image.